Fab 36 power plant operational on time |
|
|
|
Sep 14, 2005 at 05:45 PM |
|
Plant
constructor and service provider M+W Zander has completed the energy supply
center " EVC 2" for the second AMD chip plant in Dresden, Fab 36 at a cost of
66 million Euros.
The energy
center is operated by ‘Zweite Energieversorgungscenter Dresden-Wilschdorf GmbH
& Co KG', a joint-venture between the industrial gas supplier Air Liquide,
Düsseldorf, and the local energy supplier DREWAG. The new energy supply centre
EVC 2 provides the AMD Fab 36 with electrical power, hot and cold water through
a thermal power station powered by natural gas. The capacity would be adequate
to supply all the energy necessary for a town with 150,000 inhabitants.
The first gas
generator started up pilot operation in November 2004. The EVC 2 has been
supplying all the energy for the AMD Fab 36 since the first of April 2005.
|